Interconnection queue › Nevada › Geothermal
Snapshot of 2026-08-09 · 19 projects
19 geothermal projects are in the interconnection queue with a Nevada location, totalling 1,509 MW across the 19 that publish a capacity.
Get told what moves in geothermal in Nevada
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in geothermal in Nevada: what entered, what moved study phase, what came off the list.
Email me geothermal in Nevada queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| CAISO | 19 | 1,509 MW |
| Status | Projects |
|---|---|
| WITHDRAWN | 18 |
| COMPLETED | 1 |
| County | Projects | Capacity |
|---|---|---|
| CHURCHILL | 13 | 552 MW |
| MINERAL | 3 | 239 MW |
| ESMERALDA COUNTY | 2 | 627 MW |
| CHURCH | 1 | 90 MW |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | County | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|---|
| ALUM GEOTHERMAL | CAISO | ESMERALDA COUNTY | 427 | WITHDRAWN | 2021-04-15 | not published |
| PEARL GEOTHERMAL | CAISO | ESMERALDA COUNTY | 200 | WITHDRAWN | 2021-04-15 | not published |
| GREEN BORDERS GEOTHERMAL PHASE 2 | CAISO | MINERAL | 150 | WITHDRAWN | 2007-03-06 | not published |
| GREEN BORDERS GEOTHERMAL PHASE II | CAISO | CHURCH | 90 | WITHDRAWN | 2006-11-16 | not published |
| COYOTE CANYON | CAISO | CHURCHILL | 70 | WITHDRAWN | 2011-03-31 | not published |
| GREEN BORDERS GEOTHERMAL | CAISO | MINERAL | 62 | WITHDRAWN | 2005-02-22 | not published |
| NYC #1 | CAISO | CHURCHILL | 61 | WITHDRAWN | 2008-05-29 | not published |
| DIXIE MEADOWS #1 | CAISO | CHURCHILL | 61 | WITHDRAWN | 2008-05-29 | not published |
| TGDV #1 | CAISO | CHURCHILL | 61 | WITHDRAWN | 2008-05-29 | not published |
| TGDV#2 | CAISO | CHURCHILL | 61 | WITHDRAWN | 2008-05-29 | not published |
| NYC #2 | CAISO | CHURCHILL | 52 | WITHDRAWN | 2008-05-29 | not published |
| DIXIE MEADOWS #2 | CAISO | CHURCHILL | 52 | WITHDRAWN | 2008-05-29 | not published |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| CAISO | 2026-08-09 | 2026-08-09 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.