Kings County, New York Interconnection Queue
Snapshot of 2026-09-07 · 43 projects · New York (NY)
There are 43 projects in the interconnection queue located in Kings County, New York (NY), totaling 23,495 MW across the 40 that publish a capacity.
Technology in Kings County
See what moved in Kings County, New York each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in Kings County, New York, from new entries to projects that came off the list.
Email me Kings County, New York queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| NYISO | 43 | 23,495 MW |
By fuel, as published
Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here. The national table is the only place any fuel code is mapped.
| Fuel | Projects | Capacity |
|---|---|---|
| ES | 17 | 1,811 MW |
| W | 10 | 12,639 MW |
| CT | 6 | 985 MW |
| DC | 4 | 5,100 MW |
| (not published) | 2 | not published |
| OSW | 1 | 1,310 MW |
| CC | 1 | 1,100 MW |
| H | 1 | 550 MW |
| AC | 1 | not published |
By status, as published
| Status | Projects | Capacity |
|---|---|---|
| Withdrawn | 36 | 20,822 MW |
| Active | 4 | 1,166 MW |
| Cluster Study | 3 | 1,507 MW |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Atlantic Shores Offshore Wind Bight 1 | NYISO | 2,100 | Withdrawn | 2022-02-25 | not published |
| Atlantic Shores Offshore Wind Bight 4 | NYISO | 2,100 | Withdrawn | 2022-02-25 | not published |
| AGR NY-1 | NYISO | 1,600 | Withdrawn | 2022-02-17 | not published |
| OW Ocean Winds East 7 | NYISO | 1,600 | Withdrawn | 2022-05-02 | not published |
| Hera Power Link 1500 | NYISO | 1,500 | Withdrawn | 2023-11-02 | not published |
| Vineyard Mid-Atlantic 1 | NYISO | 1,350 | Withdrawn | 2022-08-24 | not published |
| Vineyard Northeast 2 | NYISO | 1,345 | Withdrawn | 2022-10-31 | not published |
| Bluepoint Wind 1 | NYISO | 1,310 | Cluster Study | 2024-08-01 | 12-2033 |
| Project Neptune DC NB-NYC | NYISO | 1,200 | Withdrawn | 2000-01-21 | not published |
| NY City Offshore Wind | NYISO | 1,200 | Withdrawn | 2017-11-07 | not published |
| Hera Power Link 1200 | NYISO | 1,200 | Withdrawn | 2023-11-02 | not published |
| TransGas Energy | NYISO | 1,100 | Withdrawn | 2001-10-05 | not published |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| NYISO | 2026-09-07 | 2026-08-13 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.