Interconnection queue › Massachusetts › Bristol County › Hybrid
Hybrid Projects in Bristol County, Massachusetts
Snapshot of 2026-09-07 · 16 projects
16 hybrid projects are in the interconnection queue in Bristol County, Massachusetts, totaling 170 MW across the 16 that publish a capacity.
See what moved in hybrid in Bristol County, Massachusetts each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in hybrid in Bristol County, Massachusetts, from new entries to projects that came off the list.
Email me hybrid in Bristol County, Massachusetts queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| ISO-NE | 16 | 170 MW |
By fuel code, as published
| Fuel | Projects | Capacity |
|---|---|---|
| SUN BAT | 16 | 170 MW |
By status, as published
| Status | Projects |
|---|---|
| (not published) | 16 |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Eversource Group @ Industrial Park 636 | ISO-NE | 29 | not published | 4/9/2020 | 11/30/2023 |
| Eversource Group @ Fisher Rd Substation 657 | ISO-NE | 28 | not published | 4/9/2020 | 11/30/2023 |
| Eversource Group @ Wing Lane 624 | ISO-NE | 19 | not published | 4/9/2020 | 11/30/2023 |
| Group @ Industrial Park 636 - EMA ASO | ISO-NE | 17 | not published | 6/8/2022 | 11/30/2023 |
| Group @ Wing Lane 624 - EMA ASO | ISO-NE | 15 | not published | 6/8/2022 | 11/30/2023 |
| Eversource Group @ Bell Rock #661 | ISO-NE | 12 | not published | 6/23/2020 | 11/30/2023 |
| Eversource Group Study @ Industrial Park | ISO-NE | 11 | not published | 3/25/2020 | 11/30/2023 |
| Eversource Group @ Cross Rd 651 | ISO-NE | 10 | not published | 4/9/2020 | 11/30/2023 |
| Eversource Group @ Arsene St 654 | ISO-NE | 7 | not published | 4/9/2020 | 11/30/2023 |
| EE 2024 SEMA/Cape ASO Group Study | ISO-NE | 5 | not published | 5/8/2024 | 12/31/2026 |
| Solar plus Battery | ISO-NE | 5 | not published | 3/25/2020 | 11/30/2023 |
| EE 2024 SEMA/Cape ASO Group Study | ISO-NE | 5 | not published | 5/8/2024 | 12/31/2026 |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| ISO-NE | 2026-09-07 | 2026-09-07 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.