Interconnection queue › California › Kings County › Solar
Solar Projects in Kings County, California
Snapshot of 2026-09-07 · 73 projects
73 solar projects are in the interconnection queue in Kings County, California, totaling 8,602 MW across the 73 that publish a capacity.
See what moved in solar in Kings County, California each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in solar in Kings County, California, from new entries to projects that came off the list.
Email me solar in Kings County, California queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| CAISO | 73 | 8,602 MW |
By fuel code, as published
| Fuel | Projects | Capacity |
|---|---|---|
| Solar | 73 | 8,602 MW |
By status, as published
| Status | Projects |
|---|---|
| WITHDRAWN | 50 |
| COMPLETED | 16 |
| ACTIVE | 7 |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| PLUM | CAISO | 1,000 | ACTIVE | 2021-04-15 | not published |
| WSP 3 | CAISO | 800 | WITHDRAWN | 2011-03-31 | not published |
| VALLEY OAK SOLAR | CAISO | 600 | WITHDRAWN | 2010-07-31 | not published |
| OATFIELD HYBRID SOLAR | CAISO | 500 | WITHDRAWN | 2019-04-15 | not published |
| MADISON SOLAR | CAISO | 500 | WITHDRAWN | 2011-03-31 | not published |
| VALLEY SUNLIGHT REFINERY | CAISO | 400 | WITHDRAWN | 2021-04-15 | not published |
| SLATE | CAISO | 300 | COMPLETED | 2015-04-30 | not published |
| DAYLIGHT | CAISO | 300 | ACTIVE | 2016-05-02 | not published |
| AQUAMARINE WESTSIDE | CAISO | 250 | COMPLETED | 2015-04-30 | not published |
| WESTLANDS SOLAR BLUE | CAISO | 250 | COMPLETED | 2015-04-30 | not published |
| KINGSOLAR II | CAISO | 250 | WITHDRAWN | 2010-02-01 | not published |
| WESTLANDS LEMOORE SOLAR | CAISO | 250 | WITHDRAWN | 2011-03-31 | not published |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| CAISO | 2026-09-07 | 2026-09-07 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.