Interconnection queue › Arizona › Maricopa County › Solar
Solar Projects in Maricopa County, Arizona
Snapshot of 2026-09-07 · 25 projects
25 solar projects are in the interconnection queue in Maricopa County, Arizona, totaling 7,552 MW across the 25 that publish a capacity.
See what moved in solar in Maricopa County, Arizona each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in solar in Maricopa County, Arizona, from new entries to projects that came off the list.
Email me solar in Maricopa County, Arizona queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| CAISO | 25 | 7,552 MW |
By fuel code, as published
| Fuel | Projects | Capacity |
|---|---|---|
| Solar | 25 | 7,552 MW |
By status, as published
| Status | Projects |
|---|---|
| WITHDRAWN | 17 |
| COMPLETED | 6 |
| ACTIVE | 2 |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| AZ BIGHORN | CAISO | 900 | WITHDRAWN | 2008-05-29 | not published |
| HYDER | CAISO | 800 | WITHDRAWN | 2021-04-15 | not published |
| CVH POWER II | CAISO | 700 | WITHDRAWN | 2011-03-31 | not published |
| HARQUAHALA SOLAR | CAISO | 515 | WITHDRAWN | 2016-05-02 | not published |
| LA PAZ | CAISO | 500 | WITHDRAWN | 2020-04-15 | not published |
| HARQUAHALA FLATS | CAISO | 450 | WITHDRAWN | 2017-05-01 | not published |
| CENTURY SOLAR | CAISO | 307 | WITHDRAWN | 2016-05-02 | not published |
| PAPAGO | CAISO | 300 | WITHDRAWN | 2020-04-15 | not published |
| HYDER | CAISO | 300 | WITHDRAWN | 2008-05-29 | not published |
| CVH POWER I | CAISO | 300 | WITHDRAWN | 2011-03-31 | not published |
| HYDER VALLEY SOLAR ENERGY | CAISO | 300 | WITHDRAWN | 2013-04-30 | not published |
| CALIENTE SOLAR ENERGY | CAISO | 250 | WITHDRAWN | 2008-05-30 | not published |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| CAISO | 2026-09-07 | 2026-09-07 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.