Interconnection queue › Texas › Gas
Snapshot of 2026-08-10 · 19 projects
Coverage note: ERCOT, the grid operator for most of Texas, is not observed here — its published files disallow automated collection. MISO, which reaches a strip of eastern Texas, is withheld too: it blocks a collector that identifies itself, and we will not impersonate a browser to resell the data. What remains is the SPP panhandle, so this page covers only the SPP portion of Texas.
19 gas projects are in the interconnection queue with a Texas location, totalling 4,962 MW across the 19 that publish a capacity.
Get told what moves in gas in Texas
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in gas in Texas: what entered, what moved study phase, what came off the list.
Email me gas in Texas queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| SPP | 19 | 4,962 MW |
| Status | Projects |
|---|---|
| IA FULLY EXECUTED/COMMERCIAL OPERATION | 12 |
| DISIS STAGE | 2 |
| IA FULLY EXECUTED/ON SCHEDULE | 2 |
| ERAS | 2 |
| IA PENDING | 1 |
| County | Projects | Capacity |
|---|---|---|
| Hale | 4 | 777 MW |
| Yoakum | 3 | 21 MW |
| Harrison | 2 | 1,585 MW |
| Denver City | 2 | 325 MW |
| Morris | 1 | 915 MW |
| Hallsville | 1 | 513 MW |
| Gaines | 1 | 17 MW |
| Hale County | 1 | 5 MW |
| Lubbock | 1 | 205 MW |
| Denver City/Yoakum | 1 | 150 MW |
| Earth | 1 | 232 MW |
| Abernathy | 1 | 217 MW |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | County | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|---|
| GEN-2024-377 | SPP | Harrison | 1,350 | DISIS STAGE | 3/1/2025 | 12/15/2031 |
| GEN-2023-204 | SPP | Morris | 915 | IA PENDING | 10/2/2023 | 12/1/2028 |
| GEN-2022-GR1 | SPP | Hallsville | 513 | IA FULLY EXECUTED/ON SCHEDULE | 3/23/2022 | 12/15/2027 |
| GEN-2024-343 | SPP | Harrison | 235 | DISIS STAGE | 3/1/2025 | 6/1/2030 |
| ERAS-2025-016 | SPP | Earth | 232 | ERAS | 10/2/2025 | 6/1/2029 |
| ERAS-2025-002 | SPP | Abernathy | 217 | ERAS | 9/12/2025 | 2/28/2027 |
| GEN-2010-006 | SPP | Lubbock | 205 | IA FULLY EXECUTED/COMMERCIAL OPERATION | 3/24/2010 | 6/30/2011 |
| GEN-2012-037 | SPP | Hale | 203 | IA FULLY EXECUTED/COMMERCIAL OPERATION | 9/30/2012 | 3/1/2015 |
| IFS-2013-001-03 | SPP | Hale | 203 | IA FULLY EXECUTED/COMMERCIAL OPERATION | 3/29/2013 | 10/19/2019 |
| GEN-2022-147 | SPP | Hale | 203 | IA FULLY EXECUTED/ON SCHEDULE | 2/21/2023 | 12/11/2026 |
| GEN-2011-048 | SPP | Denver City | 175 | IA FULLY EXECUTED/COMMERCIAL OPERATION | 9/30/2011 | 3/1/2013 |
| GEN-2006-018 | SPP | Hale | 168 | IA FULLY EXECUTED/COMMERCIAL OPERATION | 6/1/2010 | 3/22/2011 |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| SPP | 2026-08-10 | 2026-08-10 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.